08.08.2014

Siberwood LLC has come to a final stage in its pre-engineering work on the project. Significant results have been achieved. Here are some of the most important highlights:

  • working together with the partner companies we have drawn a technical concept of the mill which meets toughest environmental requirements as well as manufacturing efficiency standards;
  • we have completed negotiations with equipment suppliers;
  • together with partners and international development institutes we developed optimal structure for project financing;
  • wood resource base has been studied and selected. Also, we have completed all the necessary paperwork to obtain a "Priority" status of porject in forestry sector.
22.05.2014

22.05.2014 General project hearing was kept in regional Ust-Kut administration. The topic of the hearing was "Declaration of intent of construction of a pulp mill factory in Ust-Kut Region".
The presentation was delivered by CEO of Siberwood LLC Malkov S. "The Ecological Impact" part of the general presentation was deliver by independent consultant Shoshina L., director of Ecological Consulting Centre.

21.04.2014

JSC ”Sibgiprobum” (Irkutsk) has accomplished the Declaration of Intent for wood-processing complex construction by Siberwood Ltd. in the city of Ust-Kut, Irkutsk region.
The declaration has been worked out according to requirements of the Russian Federation regulation issued by the Minister of Construction came in force as of March, 17th 1997 # 9-4/29 and approved by the Ministry of Natural Resources.

15.04.2014

Environmental survey has been completed by Ecological Consulting Centre, Arkhangelsk. The survey's focus was environmental impact of construction of forestry and chemical complex for pulp production by Siberwood LLC. Ecological Consulting Centre's report states that overall ecological impact of the chosen technology will be within acceptable norms.
Following conclusions have been highlighted in the report: